Job with negative priority

Viewing 2 posts - 1 through 2 (of 2 total)
  • 18th March 2021 at 1:03 pm #34358

    At the moment we are rendering a huge animation, just for our selves. It is going to take a few weeks to render.
    But in the meanwhile we are rendering other jobs as well for our customers.

    Is it possible to give the animation something like a negative priority? So when what ever other job is submitted that one goes first and as soon as these jobs are finished it will go on with the animation ?

    19th March 2021 at 2:11 pm #34359

    Hi there,

    There’s no support for negative priority but you can use priority up to 65535 so you can reserve lower priorities for your customers.